Dewey Beach Town Manager Bill Zolper gives a tour of the new town hall facility Jan. 14. When finished, the building will hold town administration, the alderman court, parking enforcement, the police department and an EMS quarters. ELLEN MCINTYRE PHOTOS
The new Dewey Beach town hall is being constructed at 1505 Coastal Hwy, next to Grotto Pizza. NICK ROTH PHOTO
Town Manager Bill Zolper walks through the building’s second-floor hallway.
The current town hall, located on Rodney Avenue, is right next to the new town hall that is under construction. NICK ROTH PHOTO
The second floor has a ways to go, but the contractors are making good progress. Straight ahead will be a large meeting room for town council and committee meetings. To the left is a balcony.
Dewey Beach Town Manager Bill Zolper describes how the town will use the space in the new facility.
Costello Construction workers are making progress on the second floor of the building, which will contain meeting and office spaces.
This wall, located on the first floor to the right of the front door, will showcase the donor wall featuring the names of folks who donate to the project, along with photos of the town, information about its history and more.
The third floor of the building will be used for storage.
On the first floor, there are cinder block holding cells that the police department will use for people being detained. Each cell will have a toilet, sink and drain. A shower will be placed at the end of the hall.
Dewey Beach Town Manager Bill Zolper gives a tour of the new town hall facility Jan. 14. When finished, the building will hold town administration, the alderman court, parking enforcement, the police department and an EMS quarters. ELLEN MCINTYRE PHOTOS
The new Dewey Beach town hall is being constructed at 1505 Coastal Hwy, next to Grotto Pizza. NICK ROTH PHOTO
Town Manager Bill Zolper walks through the building’s second-floor hallway.
The current town hall, located on Rodney Avenue, is right next to the new town hall that is under construction. NICK ROTH PHOTO
The second floor has a ways to go, but the contractors are making good progress. Straight ahead will be a large meeting room for town council and committee meetings. To the left is a balcony.
Dewey Beach Town Manager Bill Zolper describes how the town will use the space in the new facility.
Costello Construction workers are making progress on the second floor of the building, which will contain meeting and office spaces.
This wall, located on the first floor to the right of the front door, will showcase the donor wall featuring the names of folks who donate to the project, along with photos of the town, information about its history and more.
The third floor of the building will be used for storage.
On the first floor, there are cinder block holding cells that the police department will use for people being detained. Each cell will have a toilet, sink and drain. A shower will be placed at the end of the hall.The construction of the new Dewey Beach Town Hall is moving along, with Phase 1 expected to be completed this September.
“The contractors and Costello have been very good with what they’re doing so far,” said Town Manager Bill Zolper during a tour of the facility Jan. 14. “They’re doing a good job.”
The facility, located at 1505 Coastal Hwy., will be a Risk Category IV structure, which is the highest category structure under the International Building Code. It has been designed to sustain catastrophic conditions and winds up to 127 mph, with walls and a foundation made of cement and steel.
It will feature controlled-access doors, bulletproof glass windows, and other state-of-the-art safety and security measures.
Much of the first floor will house the police department. There are multiple cinder block holding cells that will each contain a toilet, sink and drain, as opposed to the current facility, which has only one holding cell where multiple detainees may be handcuffed to the same bench.
There will also be a shower near the cells, in case any detainees need to be decontaminated.
Juvenile detainees will be brought to a different area of the building, as the law requires them to be kept separate from adults in custody.
The police will also have a locker room and storage area, which Zolper said will be especially useful in the summer, when the seasonal police officers are there.
On the second floor, there will be upgraded meeting and office spaces for town officials and administration, including the alderman court and other town staff. This includes a large room that will be used for town council and committee meetings, replacing the current meeting space at the town lifesaving station.
There is also a second-floor balcony connected to the meeting room.
The third floor will be used for storage.
Overall, the building is very spacious compared to the current one, which is cramped and outdated.
Costello Construction, the town’s contractor for the project, broke ground on Phase 1 in late April. This phase, which is estimated to take 430 days, includes constructing the town hall and police department portions of the new facility.
Phase 2, estimated to take 170 days, includes moving operations to the new building, demolishing the existing town hall and constructing an emergency medical services quarters. It will commence upon completion of Phase 1.
Funding for the project comes from various sources, including state and county grants, town capital improvement and unassigned funds, a loan and donations.
Dewey Beach Town Manager Bill Zolper gives a tour of the new town hall facility Jan. 14. When finished, the building will hold town administration, the alderman court, parking enforcement, the police department and an EMS quarters. ELLEN MCINTYRE PHOTOS
The new Dewey Beach town hall is being constructed at 1505 Coastal Hwy, next to Grotto Pizza. NICK ROTH PHOTO
Town Manager Bill Zolper walks through the building’s second-floor hallway.
The current town hall, located on Rodney Avenue, is right next to the new town hall that is under construction. NICK ROTH PHOTO
The second floor has a ways to go, but the contractors are making good progress. Straight ahead will be a large meeting room for town council and committee meetings. To the left is a balcony.
Dewey Beach Town Manager Bill Zolper describes how the town will use the space in the new facility.
Costello Construction workers are making progress on the second floor of the building, which will contain meeting and office spaces.
This wall, located on the first floor to the right of the front door, will showcase the donor wall featuring the names of folks who donate to the project, along with photos of the town, information about its history and more.
The third floor of the building will be used for storage.
On the first floor, there are cinder block holding cells that the police department will use for people being detained. Each cell will have a toilet, sink and drain. A shower will be placed at the end of the hall.